Call for Construction of Two Solar Safe Drinking Water Stations in Oddar Meanchey Province
Oxfam is a global movement of people who are fighting inequality to end poverty and injustice. Across regions, from the local to the global, we work with people to bring change that lasts.
|
OVERVIEW |
|
|
Start date |
December 2026-Janaury 2027 |
|
Project |
Climate Resilience for All (CREFA) Project |
|
Location |
Pongo Commune, Chong Kal District, Oddar Meanchey Province |
|
Number of Stations |
Two (2) Stations |
|
Water sources |
Community Pond |
|
People to serve |
More than 816 families with a preliminary population of approximately 3,203 people |
|
Contract type |
Design, supply, build, test, and hand over; lump-sum price in USD |
|
Duration |
All work finished within 30-45 calendar days after contract signing |
|
Completion Date |
January 25, 2027 |
|
Handover |
Checked and accepted by a Handover and Evaluation Committee (Oxfam, Oddar Meanchey provincial department, commune and community committee) |
|
How to apply |
Proposal must include:
Via the link below:
https://jobs.oxfamnovib.nl/job-invite/14563/
|
|
Deadline |
30 November 2026 |
|
For any questions |
please contact us via this email: CLV.HR@oxfam.org |
BACKGROUND AND CONTEXT
The Climate Resilience for All (CREFA) Project is a four-year initiative running from February 2024 to January 2028 under Oxfam's Natural Resource Governance (NRG) Programme. Funded by the Government of Ireland's International Development Programme through the Embassy of Ireland in Hanoi, the project is implemented by Oxfam in Cambodia in collaboration with nine consortium partners.
CREFA aims to reduce climate vulnerability and strengthen the resilience of Cambodian communities through a twin-track approach that combines strengthening policy dialogue and governance with enhancing the adaptive capacity of local communities. The project focuses on promoting climate-smart agriculture, renewable energy, community resilience, and policy engagement. The project operates across five provinces: Battambang, Banteay Meanchey, Oddar Meanchey, Siem Reap, and Preah Vihear. Its interventions directly engage with 19 community forests and community protected areas, five community fisheries, and four community-owned solar irrigation systems.
However, the Cambodia–Thailand border conflict in 2025 significantly disrupted the livelihoods and living conditions of communities in and around the affected areas, including several communities supported by CREFA. The resulting displacement and insecurity have further increased the vulnerability of affected households and disrupted their access to essential services, particularly safe drinking water. Furthermore, the impacts of climate change, particularly the anticipated El Niño conditions, are expected to place additional pressure on already vulnerable displaced communities. Rising temperatures, prolonged dry spells, and reduced rainfall may exacerbate water scarcity, increase pressure on limited water resources, and make it more difficult for displacement camps to meet the daily water needs of affected families. These conditions could further increase public health risks, particularly for women, children, older people, and other vulnerable groups. Therefore, ensuring a reliable supply of safe drinking water is increasingly urgent to protect the health and well-being of displaced households and strengthen their resilience to climate-related shocks. In response, Oxfam in Cambodia, through CREFA, is extending support to vulnerable displaced communities in Oddar Meanchey Province to address urgent basic needs and contribute to their recovery and resilience.
SRAH KEO RESETTLED VILLAGE
Srah Keo Resettled Village is located in Pongro Commune, Chong Kal District, Oddar Meanchey Province, along Cambodia's northwestern border with Thailand. The Resettled Village accommodates 816 displaced families, comprising 3,203 people, including 1,579 women and 933 children, who were relocated from Krong Samrong and Banteay Ampil due to border tensions and insecurity. Established with support from the World Bank's Land Allocation for Social and Economic Development (LASED III) Project, the settlement provides displaced families with an opportunity to rebuild their lives. Basic services have gradually been established, including primary school, a health center, and livelihood support through agricultural inputs and livestock.
Despite these developments, access to safe drinking water remains one of the community's most pressing challenges. Although water sources are available within the settlement, their quality is not consistently suitable for drinking. Consequently, many households must purchase clean drinking water to meet their daily needs, placing additional financial pressure on families already facing limited income opportunities, existing debt burdens, and increased living costs following displacement. Limited access to safe drinking water also presents risks to public health, hygiene, and household well-being, particularly for women, children, people with disabilities and other vulnerable groups. Improving access to safe and affordable drinking water is therefore an essential priority for supporting the community's recovery, health, and dignity.
Recognizing this urgent need, Oxfam in Cambodia, through the CREFA Project, proposes to establish two solar-powered safe drinking water stations in Srah Keo Resettled Village. The stations will utilize existing community ponds as their primary water sources, with solar-powered pumping systems supplying water for treatment through a multi-stage process comprising sand filtration, activated carbon filtration, Reverse Osmosis (RO), and Ultraviolet (UV) disinfection. The treated water will then be stored and made available to the community through public water collection taps.
The intervention aims to improve access to safe, reliable, and affordable drinking water for 816 displaced families (approximately 3,203 people), reduce household expenditure on purchased drinking water, and contribute to better public health, dignity, and well-being as families rebuild their lives.
OBJECTIVES OF THE ASSIGNMENT
The overall objective is to establish two fully operational solar-powered safe drinking water stations using existing community pond water, providing reliable access to safe drinking water for more 816 displaced families that meets the Cambodian Drinking Water Quality Standard.
By the end of the assignment, Oxfam expects the following results:
- Two (2) fully functional solar-powered safe drinking water stations constructed, tested, commissioned, and handed over within 30–45 calendar days of contract signing, and no later than 25 January 2027.
- Treated water tested by an accredited laboratory in Cambodia and confirmed to meet applicable Cambodian drinking-water quality standards.
- Each Reverse Osmosis (RO) unit capable of producing 250–300 litres of treated water per hour.
- Local caretaker teams are trained and able to operate, clean, and carry out basic maintenance of the systems.
- All defects identified during the warranty period repaired by the contractor at no additional cost to Oxfam.
SCOPE OF WORK
The Contractor shall be responsible for the complete design, supply, construction, installation, testing and handover of two solar-powered water supply station. The scope of work shall include a steel tower equipped with a 4,000-litre water storage tank, a treatment shed beneath the tower, a water treatment system, public water taps, solar power supply and signage.
The specifications outlined below represent the minimum requirements. The Contractor may propose alternative or enhanced solutions in its technical proposal, if these are supported by appropriate justification. All works shall be carried out in accordance with the Bill of Quantities (BOQ), technical specifications, approved drawings, and approved product samples or catalogues.
Prior to commencing construction, the Contractor shall conduct a site visit, assess and verify both water sources, and submit a preliminary design package to Oxfam for review and approval. The package shall include a site layout drawing, process flow drawing and corresponding Bill of Quantities.
4.1 Site assessment and community pond investigation
- Conduct site assessments of both proposed stations and community ponds in coordination with Oxfam, local authorities, and community representatives.
- Assess pond conditions, water availability, seasonal fluctuations, and potential contamination risks.
- Collect and arrange laboratory testing of raw water samples to inform the treatment system design.
- Identify suitable water intake locations and methods to minimise sediment, debris, and algae.
- Prepare a site assessment report outlining key findings, risks, and recommendations.
-
- Engineering design and technical drawings
The contractor shall prepare a complete design package for each station, including:
- Pond intake structure and raw water tanks with (sand filter and active charcoal/carbon filter tanks), screening system, raw-water pipelines, and pump layout.
- Solar PV layout, electrical design, energy calculations, and protection systems.
- Pump specifications, hydraulic calculations, flow rates, and total dynamic head.
- Water treatment process flow diagram, equipment specifications, design capacity, and expected treatment performance.
- Treated-water storage tank, supporting tower, foundations, and structural calculations.
- Treatment and equipment room design, including roofing, ventilation, access, and drainage.
- Water distribution pipelines, public taps, collection areas, and wastewater drainage arrangements.
- Site safety measures, fencing, signage, and maintenance access.
- Itemised Bill of Quantities (BoQ), cost estimates, and implementation schedule.
All designs, technical drawings, specifications, and BoQs must be submitted to Oxfam for written approval before construction or installation. Oxfam's review does not remove the contractor's responsibility for the adequacy and safety of its design.
4.3 Construction and installation
The contractor shall supply, construct, install, connect, and integrate all components required for each station to operate as a complete system. This includes pond intake and screening, solar-powered pumping, solar modules and controls, pre-treatment, filtration and disinfection, treated-water storage, steel tower/platform, treatment room, roofing, distribution taps and pipelines, drainage, fencing, signage, and all necessary fittings and accessories.
MINIMUM TECHNICAL SPECIFICATIONS AND STANDARDS
The requirements below are minimum requirements. Bidders may propose technically superior alternatives, if they demonstrate suitability for the tested pond water, meet drinking-water safety requirements, are maintainable locally, and remain within the approved budget. Final sizing shall be based on site investigation and approved calculations.
For detailed minimum technical specifications and standards, minimum design and service capacity, required contents of the technical and financial proposal technical proposal, health, safety, environmental, and safeguarding requirements, Oxfam's responsibilities, and the contractor's responsibilities
*** Please refer to Annex 01
DELIVERABLES
|
Deliverable |
Description |
|
Inception and site assessment report |
Site conditions, pond assessment, seasonal water availability, user demand, risks, and recommendations. |
|
Raw-water quality report |
Laboratory results for raw pond water from the source(s) serving both stations. |
|
Engineering design package |
Detailed drawings, process flow diagram, technical specifications, hydraulic and solar calculations, structural calculations, and treatment design. |
|
BoQ and implementation work plan |
Itemised BoQ, cost breakdown, material specifications, procurement schedule, and construction schedule. |
|
Construction and installation |
Two complete stations installed in accordance with approved designs and specifications. |
|
Testing and commissioning report |
Pumping and solar performance, treatment operation, water-quality results, electrical safety checks, and corrective actions if any. |
|
Training and O&M package |
Operator training, manuals in English and key operating instructions in Khmer, maintenance schedules, and troubleshooting guidance. |
|
Final handover report |
As-built drawings, equipment inventory, warranties, certificates, laboratory reports, manuals, photographs, and signed handover records. |
IMPLEMENTATION PERIOD AND COMPLETION DEADLINE
The assignment shall be completed within 30–45 calendar days from the date of contract signing, with an absolute completion deadline of 25 January 2027. The contractor shall mobilise immediately after signing.
|
Activities |
Indicative timeline |
|
Contract signing, mobilisation, site and pond assessment, water sampling |
Days 1–7 |
|
Laboratory testing, engineering design, BoQ, and Oxfam approval |
Days 5–12 |
|
Procurement and delivery of materials and equipment |
Days 10–20 |
|
Civil works, pond intake, tower, treatment room, solar and equipment installation |
Days 15–35 |
|
Treatment integration, system testing, and commissioning |
Days 30–40 |
|
Treated-water verification, operator training, documentation, and handover |
Days 40–45 |
CONTRACTOR QUALIFICATIONS AND EXPERIENCE
Interested contractors must demonstrate the following minimum qualifications:
- Legally registered company or business entity in Cambodia, with relevant authorisations to undertake the works.
- At least three years of relevant experience in water supply infrastructure, solar-powered pumping, water treatment, or comparable works.
- Experience delivering at least two comparable water supply or solar-powered water infrastructure projects; experience with surface-water treatment is strongly preferred.
- Access to qualified personnel, including a water supply/hydraulic engineer, water-treatment specialist or qualified technician, solar/electrical technician or engineer, and civil/structural engineer.
- Capacity to procure, transport, install, test, and commission the systems within the required timeframe.
- Ability to arrange competent laboratory testing of drinking-water quality.
- Able to start work quickly and work safely in a camp with many children and vulnerable people.
- Commitment to Oxfam's safeguarding, health and safety, environmental, and ethical procurement requirements.
Key Attributes:
- Ability to demonstrate sensitivity to cultural differences and gender issues, as well as the commitment to equal opportunities.
- Ability to demonstrate an openness and willingness to learn about the application of gender/gender mainstreaming, women’s rights, and diversity for all aspects of development work.
- Commitment to Oxfam’s safeguarding policies to ensure all people who come into contact with Oxfam are as safe as possible.
Organisational Values:
- Accountability – Our purpose-driven, results-focused approach means we take responsibility for our actions and hold ourselves accountable. We believe that others should also be held accountable for their actions.
- Empowerment – Our approach means that everyone involved with Oxfam, from our staff and supporters to people living in poverty, should feel they can make change happen.
- Inclusiveness – We are open to everyone and embrace diversity. We believe everyone has a contribution to make, regardless of visible and invisible differences.
Others:
- Eager and required to adhere to Oxfam’s principles and values as well as the promotion of gender justice and women's rights.
- Understanding of and commitment to adhere to equity, diversity, gender, child safety and staff health and wellbeing principles.